| Thursday June 22  The day shift began with Operations monitoring a Recycler stash, with the Tevatron (TeV) recovering from a quench, with the Collider Detector at Fermilab (CDF) and D-Zero (D0) waiting for colliding beam, with the Antiproton Source (Pbar) stacking, with the Main Injector (MI) and Recycler conducting studies, and with MiniBooNE and NuMI taking beam. Operations put the TeV into a dry squeeze at 9:34 AM. Operations began preparing the Recycler at 9:39 AM to stash antiprotons. The stash ended and Pbar resumed stacking at 10:17 AM. Operations added an event at 10:21 AM to the time line for Switchyard (SY) experts to conduct a study. They eventually got beam to F17. TeV experts reported at 2:10 PM that they understood the problem with the orbit stabilization program. Experts completed a kicker study and then began a chromaticity study. The Recycler began preparing to stash at 6:32 PM. The stash ended and Pbar resumed stacking at 7:40 PM. TeV experts completed their studies at 7:42 PM. Operations put the TeV into shot setup at 8:38 PM. Operations established store 4794 at 11:40 PM with an initial luminosity of 61.4E30. Friday June 23  The midnight shift began with Operations monitoring store 4794 and the stash, with Pbar stacking, with normal MI, Recycler, SY, and Booster conducting studies, and with MiniBooNE and NuMI taking beam. The Recycler began preparing to stash at 1:36 AM. At 2:19 AM, the NuMI beam permit tripped off on a target LCW flow indication. Ten minutes later, a NuMI expert directed operators to reset the beam permit and run at a lower intensity. The stash ended and Pbar resumed stacking at 2:37 AM. The Recycler began preparing to stash at 7:10 AM. The stash ended and Pbar resumed stacking at 7:56 AM. The Plans for Friday and the Weekend  The plans for today are to allow TeV experts to conduct end-of-store studies. Booster experts will conduct two two-hour studies: one destructive and the other at low intensity. The weekend will consist of stacking, stashing, and storing.  Machine Reports  Tevatron  
 Problems 
                      Flying wires still report sigmas okay, but the data calculated by OAC that fills the reports are still invalidD0 reported that proton halo losses are higher than 2005, found that D0 vacuum is worse 
 Work Done This Week 
                      Have CDF and D0 IP position changes ready to implement waiting for an end of storeMeasured alpha bumps at CDF and D0 and implemented a vertical change at D0 of ~ 20cmTested new application that can measure coupling and calibrated SQ and SQA0 mults used for shot setup tuningInvestigated why the C100, chromaticity measurement application used in shot setup is not working Work For Next Week 
                      Need to move positions for CDF and D0 Linac  Last Week Summary 
                      Running on the H- Ion SourceBeam positions Started Out Normal, but After Tank 5 Quad Shorted they Retuned, which Resulted in better positionsDowntime 5.94 Hours With 31 Occurrences Major Sources of Downtime
                         Klystron 4 Phase Problems .64 hrTank 5 Quad #20 Shorted to Ground 3.94 hr Problems 
                      TRIM90 current was wandering and we replaced the supplyDebuncher Water Skid Tripped Several Times Booster  Summary 
                      Continued to work on orbitsAdded second notcher (L12 kicker)Changed 400 MeV control processor
                        Trying to speed up power supply controls Worked on dampers
                        Quad damper on, mode 49 still off Gamma –t and sum resonance studiesMight start collimator work today First Notcher 
 Second Notcher 
 Next Week 
                      Secondary Collimators (starting today)Dampers will get tuned with higher intensity RF work – several weak stationsBeam position survey Main Injector  MI 
                      I68 problem.
                        120 GeV antiproton production120 Slow spill MI BPM upgrade 
                      MI30 BPMs are converted to run on new system. New BLM system 
                      Still trying to debug the new system at MI40The BLMs in MI30 were still with multibus system. Antiproton Source  Last Week 
                      First “routine” week since shutdown. Nearly entire week spent stacking, tuningMajor downtime ~ 1 shift (Mon owl) for M:HV102 supplyBest stacking rate ~ 13 E10/hr (vs. 20 in February)Beam on target ~ 5.5E12 (vs. full intensity of 8.0) Things To Do 
                      Yield to end of AP2 line same as before shutdown
                        Need to streamline/calibrate intermediate stacking efficiencies for Debuncher, D→A, etc. We need to measure A:PRDCTN vs. beam on target and vs. cycle time, to understand our bottlenecks
                        Get PRDCTN back to 21 and keep it there at full rate Access task list growing: Deb tank, CV1, QS732, TOR724, VT726, VT716, M:Q209, AP1 OTRWould be fantastic to have hard-wired Ethernet connection to F23 and F27 for BPM readout (AP1, AP2, AP3) MiniBooNE  Horn Supply Failure 
                      Began about 22:00, Sunday. Experts called in.Traced to arcing in supply. This damaged the connection between two Stripline busses. Shut down.Monday, EE support removed damaged components and fabricated replacementsTuesday, repaired horn and did thermal imagingSmooth running since then 
 Accelerator Update Archive More InformationFor Tevatron luminosity charts and the current status of Fermilab's accelerators and detectors (live!), please go to Fermilab Now.
 Comments and SuggestionsWhat do you think about the Accelerator Updates? Please send comments and suggestions to: accelupdates@fnal.gov.
 
 |