| Thursday June 1  The day shift began Operations
          with preparing the Antiproton
          Source (Pbar) and the Tevatron (TeV)
          for access.  NuMI was issued a beam permit at 8:44 AM. Experts put the TeV through a dry squeeze at 12:48 PM. The Collider Detector at Fermilab (CDF) reported at 12:58 PM that they
        were ready for beam. Operations reported at 3:20 PM the following machine status: 
         Linac is running normallyBooster is doing studiesPbar is doing studiesRecycler is doing studiesTeV is attempting to inject beamNuMI is attempting to run some beamMain Injector (MI) is looking at beam in support of TeV and NuMISwitchyard F1, F2, and F3 enclosures have been secured At 4:05 PM, the TeV suffered a quench at sector F1. Experts investigated. Operations reported that NuMI successfully took beam all the way to
        their target at 4:12 PM. Experts put the TeV through another dry squeeze at 6:23 PM. NuMI resolved some problems and resumed target scans at 6:46 PM. Operations reported at 7:08 PM a phase unbalance problem with a Debuncher
        quadrupole (D:Q731). A power supply expert came in and had it up and
        running an hour later. Booster experts ended their studies around 7:30 PM. Experts established beam in the Tevatron at 7:47 PM. Pbar experts established beam to the target at 7:50 PM. NuMI experts completed their target scans at 9:10 PM. They began a tuning
        and study period. At 10:45 PM, the TeV aborted at sector D0 due to beam positions. There
        was no quench. Pbar reported at 11:56 PM that they saw beam in AP2. Friday June 2  The day shift began with Pbar conducting stacking studies, with the
        TeV trying to circulate beam, and with NuMI taking beam. Operations reported at 4:59 AM that Pbar experts hadn’t been able
        to get beam to the Debuncher. Investigators discovered that a kicker
        (D:IKIK) power supply’s power cable had been disconnected. This
        will be further investigated during the day. TeV experts established circulating beam at 6:50 AM. Switchyard safety system tests were completed by 8 AM. The Plans for Today and the Weekend  The plan is to continue commissioning.  Machine Reports Linac  Beam Specifications 
        Running on H- SourceBeam Current ~ 34 mALoss Sum Average [< 20] Downtime 
        99.5 % Availability.85 Hours w/ 5 Occurrences Major Downtime 
        0.5 Hours à Klystron Debuncher water system trip NTF Plans for Next Week 
        Patient treatment on Monday, Tuesday and Wednesday. Studies 
        Move Collimator into Beam Line Booster  Experts continue to tune, balance the RF, and to improve the efficiency.
        Next week they need to adjust the energy and conduct a single wire scan;
        both of these items will be destructive to the beam. They also need to
        work on the following things: the orbit between periods 2 and 4, RF issues
        through transition, and to take IPM data. Main Injector  MI is supplying beam to the TeV, NuMI, and to Pbar. MI. 
        Tune up for operation as requested
          Establish 150 GeV orbit.Establish 120 GeV beam to NuMI, and Pbar. New BPM at 40
          The closed orbit mode problem was fixed. MI8 Line 
        Texas profile monitors, mw826, 827, 829, & 836.
          Fixed motion control polarity.Fixed mw826 problem of not staying in. Multiwire chambers mw839, 840, & 851.
          No signal right from start-up. Lattice study Multi-wire profiles from 826 to 852 (at 1.2e12) 
 MI8 line dispersion function 
 Next Week Linux program commissioning  BPM 
        Complete certification of new MI 40 BPM house. Studies 
        MI 8-GeV lattice measurementAperture scansTune harmonic quads at 8-GeVMI8 line Collimator
          Certify loss monitors, thermo-couples, and data logging. Effect of MPØ3 on beam to MI
          Use VT805: 3 bump to test for any sign of impact. Antiproton Source  Experts established 120 GeV beam to the target and conducted target
        scans. They have an injection kicker power problem. They are tuning with
        reverse protons. Experts hope to be stacking by Tuesday or Wednesday,
        6/6/06 or 6/7/06. Antiproton Source Startup Report 
        DVM electronic logbook titles evolved from “sad, sad story” to “fun & games”Got reverse protons to Accumulator & Debuncher by SaturdayMany little trim power supply cable swaps, etc.A power supply expert changed out D:IB contactorRepercussions of kicker 165 ® 465 ramp card swapsAccumulator aperture work. Running wave correctly identified several
          limiting apertures, e.g. tank 301 moved during leak fixAcceptances comparable to February, except Deb V, Acc Inj VPrototype tank backwards; got data Thurs; swap arrays FridayAim to remove tank (regain full Deb V acceptance) on MondayGot 120 GeV beam to target, some secondaries to end of AP2, by Thursday
          night TeV  Many little problems delayed establishing beam in the TeV. Tevatron Status 
        Looked for main bus ground fault. Did not isolate it and at times
          it has gone away.Repaired, baked, and conducted a small amount of conditioning of
          the B11 separator due to vacuum leak. E11 flying wire was found to be bad & required pulling the internal
          can for repair.Started running beam on Thursday and established the first turn on
          evening shift.Established circulating beam at 0700 this morning. Problems Establishing Beam 
        There is a new transductor for the main bus that is different by
          3.4 amps at 150gev and 22 amps at 980gev. This may mean that the program
          current is not in step with the low beta quad program. We are thinking
          about this.Required significant P1 tuning to establish beam. Recycler  Experts are ready for antiprotons. Emittance Growth 
 Orbit Corrections 
        Reversed polarity of R:H90CCorrected orbit to very close to what we had in Feb. before moving
          magnets.Bulk supply failure caused by powering skew quadsExcellent lifetimeFirst look at MI stray field compensation says same as Feb.Vert. slope on 30 straight needs work Transfer Lines 
        Protons through both transfer lines.Once MI orbit corrected, both transfer lines appear unchanged from
          Feb.Vacuum fixedStill need to make multiwires & BPMs work.Closure programs work. Acceptance 
        Worked on understanding how to make acceptance measurement.Injection acceptance was less than circulating acceptance because
          of counter waves. Reducing the counter wave fixed this.We now believe acceptance is comparable to best we’ve ever
          seen. Instrumentation 
        Ring BPMs fine, transfer line BPMs need check out.Schottky & VSA was fine, except we need a time-sampled measurement
          to see the MI effect on tune.H flying wire had a reference problem, but that’s now fixed.
          The V flying wire is fine.Transfer line multiwires need check out Lattice Function 
        An expert tried to get lattice function measurements but program
          didn’t read BPMs reliably. This is being worked on and will need
          future beam time. Operating Tunes 
        Started up at h = .414, v = .418Corrected skew quads to get min. tune split of .0014Increasing vertical tune reduces lifetime at and above .424 until
          above about .438Lifetime still not great, improved by h = .436, v = .444More studies needed. Chromaticity and Sextupoles 
        Need beam measurements to document Stochastic Cooling 
        The preliminary check out is okay, but we need antiprotons for a
          full system check.  Switchyard 120  The P3 line turn on was delayed by power supply problems. Meson Test 
        P3 dipole replacedP3 dipole LCW leak repaired in placeNew A0 quad stagedInterlock testing today through Meson primaryRun power supplies over weekendMTest interlocks next weekBeam next week if possible MiniBooNE Experts are ready for beam. (Booster will begin delivering low intensity
        beam to MiniBooNE, possibly as soon as this afternoon.) NuMI  They hit their target with the first pulse of beam. However, they still
        have a lot of little problems that need fixing. Collider Detector at Fermilab  CDF experts ran DAQ and trigger testing. D-Zero  Experts are investigating a noise problem that is possibly from their
        muon system. They also exercised their DAQ system. 
 Accelerator Update 
        Archive More InformationFor Tevatron luminosity charts and the current status of Fermilab's accelerators 
        and detectors (live!), please go to Fermilab 
        Now.
 Comments and SuggestionsWhat do you think about the Accelerator Updates? Please send comments 
        and suggestions to: accelupdates@fnal.gov.
 
 |