|  LINAC  April 7 - 14  
                      Running to NTF with the I- Ion SourceBeam Current 35 maBrought New Anode Supply On-line for the I- Haefely.Low Energy RF PM is Complete.High Energy RF PM Continued and is Complete.Characterization of the Low Energy RF Systems Continues. Troubleshooting LRF7 For the Reason It Tripped Substation 3.LRF5 Modulator Problem Found and Repaired.Found H- Haefely Problem and Repaired it. Began Assembling Cables and Equipment to Begin Checking High Energy RF Phase and Amplitude Calibration  April 14 - 21  
                      Continue Characterizing Low Energy RF SystemsPossibly Install Motor Drive for 10 MeV CollimatorContinue Test/Conditioning of Econco Switchtubes LRF7Continue Checking HE RF Phase and Gradient Readback Calibration Install New Digitizers for BPM Readbacks Linac will begin turning on for 400 MeV beam after the power outages scheduled for April 22 - 24, 2006  Booster 
                      MI-8 Extraction and Dump line under vacuum!ORBMP girder installed!400 MeV Line magnets placed/aligned
                        Connect up beam tube – start vacuum pump downMove ORBMP PS to Booster gallery Checked/Repaired water leaksRF repair/maintenance continuesSump discharge re-route continues  Schedule Issues  
                      MI-8 Dump on schedule – (tasks remaining)
                        Pull and terminate cablesInstall kickers after HV testingSepta connections and testing ORBMP – connect and test PS400 MeV PS work on schedule RF work – still lots to doLCW and sump work – still some issues 
 
 
 
  Pbar  On Schedule 
  Main Injector 
                      Continued installation of the new MI8 line multiwires. Continued installation of MI8 collimator. Completed Lambertson bakes at 608, 620. Continued installation of a large aperture quad at 101. Continued installation of large aperture quad at 402. Began installation of large aperture quad at 521,522. Installed the new loads on MI10 kickers. 
 
 Recycler  Damper Kickers  
  R32 line Vacuum Burst Investigation  
  Pelletron Work  
                      New SF6 Skid
                        Shipped todayArrive Tuesday/Wednesday of next week  Repair of the following Vacuum Components
                        IPA03 – power supply - DoneTPS S05 Replacement of shaft BearingsRepair Collector Current read back- DoneRepair Pulser switchUpgrade Fault protection systemMisc. Maintenance 
 
  Tevatron  A48 Collimator  
  B12 Quadrupole  
 TEL 1  
  Jobs Not Yet Started  
                      Re align low beta quads at B0As found A and E sectors with laser trackerA 17 separatorTEL 1 installation 
  SwitchYard They are ready to install the quadrupole at A0.  NuMI 
                      Horn 2 Repair on Schedule for Next Tuesday and Wednesday
                        Added Shielding Blocks Placed by Work Cell per ALARA Plan Target Chase Chiller Testing Started at Vendor
                        Expecting Return of Chiller by End of April Target Hall Air Dehumidification – 5 x Desiccant Units
                        Requisition Cut with Prism for Ductwork Electrical Work Continues to ProgressExploring Additional Cable Paths thru Stripline Chase Target Chase Fan Off by Noon Today. Tritium Testing Continues.Target Profile Monitor Installation Complete in Pre-Target
                        Will Survey in on Monday. Still Problems with OTR. Cleaning of Decay Pipe Passageway and Drains CompleteLevel Runs in Target Hall Completing TodayChase Condensate Tank Pump ReplacedInstallation of New Drip Ceiling in Pre-Target Started  MiniBooNE 
                      Horn
                        Initial testing April 14 (now).Complete testing week of April 17. Special LCW System
                        Week of April 24.Require special tech coverage. AlignmentConical WashersCompleted last week  Collider Detector at Fermilab On schedule  D-Zero (D0) 
                      Layer 0
                        Complete installation of junction card mountsPush Run IIb beam pipe through Layer 0 support structureConnect cooling for Layer 0Begin installing junction cards/routing cables/testing connections Level 1 Calorimeter Trigger
                        Continue connecting BLS cables to patch panels and test pulsing BLS cablesContinue firmware debugging/development/verification Level 1 Central Track Trigger
                        Continue DFEA2 output verification 
 
 
                      D-Zero attempts to minimize thermal cycles on the solenoid coils to limit risks to coil joints.
                        D sector controls apparently rebooted Friday April 7 without prior warningLoss of discharge pressure causing Mycom compressors to unloadD-Zero is dependent upon Mycom compressors powered on Feeder 46b to recover helium, and benefits from advance notice regarding anticipated changes in status of power or controls Mechanical  Work Continues  Cryogenics  Cryo Operations  
                      Tevatron at LN2 temperature and LN2 usage is stable with vendor deliveries running only 2-3 truckloads per day due to the Tevatron being 1/4 at room temperature. Helium losses are steady at 15 kscf/day (1/2 of normal during TeV operations). 
                      A1, A3, and D1 are at room temperature and isolated with LOTO.  
                      B4, E2 and F4 are also at room temperature, have been reconnected by Cryo, and are currently under normal helium flow with anticipation of Division sign-off and cooldown to LN2 temperature soon. F4 house can be cooled down to LN2 temperature without the TEL-1 installed.  A3 has been completed by MSD, though spool piece conning towers may still be retrofitted (5 out of 8 leak) by Tech Division during this shutdown. Cryo has completed epoxy of helium leaks on Tevatron power leads, though they still need a snoop leak test.Pbar D60 Debuncher vacuum work has been completed by Pbar Dept, thus Cryo personnel will restore helium/nitrogen connections and cool down tanks to LN2 temperature after Division sign-off.ACNET application programs relating to FRIG operations continue to be tested on Linux consoles. Nitrogen Reliquefier startup is delayed due to concern of “old” electrical cables being used for cross-connect between MSS and KRSS, especially due to high startup currents of 3000 hp TSI compressor. IR Booster compressor (400 hp) is running and purifying the plant.MCR monitoring cryo operations.   CHL Maintenance:  
                      General facility maintenance is in progress.CHL Helium Compr “A” cooling tower installation has been completed with painting in progress. Some minor work is left, such as electrical/controls and fencing. (PICTURE below)CHL Helium Compr “D” is being overhauled. (PICTURES below)Helium Coldbox-2 controls upgrade is in progress.   FRIG Maintenance:  
                       We have been finding some leaking quick-disconnect fittings on conning towers. We have none in stock and thus order is being placed to get spares.  
 
 
  Facility Engineering Services 
                      There’s a Booster LCW shutdown on Tuesday for pump work.Workers are cleaning the bus duct for the Master Substation.The final portion of the zebra mussel cleaning is temporarily on hold.There is ICW work on Casey’s Pond equipment.There will be a CUB LCW pump test.  Instrumentation Work continues.  RF Work continues. Controls Work continues. ES&H Upgrades  Safety System Upgrades  Keep discussing safety with your crews to keep our focus on getting our jobs done safely. 
                      Data Acquisition System CompleteP-Bar Source MiniBooNE
                        Spare Horn is okay to test EE Support They will begin conditioning the A0 kickers next week. Alignment  
                      Tevatron
                        Completed Deep Rod installation. Completed E0 Crystal Collimator Completed IPM both vert and Horiz Completed Flying wire cans at E-11. Completed Flying wires cans at E17 Schedule Drops Schedule As found two sectors.  Main Injector
                        Completed 402, and realignment of 620Completed Deep Rod installation. 8Gev
                        Completed New Texas multiwires will be installed in the MI8 line at 803, 826, 827, 829, and 836. These multiwires will need alignment. Scheduled P-Bar
                        Completed Set new AP2 beam stop on beam center once it is installed in the Transport enclosure.Deep Rod installation.  400Mev
                        Completed 400MeV Girder - Final surveyScheduled 400 MeV - Final Survey  BoosterRecycler 
                      MiniBooNENuMI
                        Completed Level run between MI-60 to NuMI SR3 (Target Hall) approx. 1500 ft.Completed NuMI Drops SR2, SR3 (Today)Schedule  
                      Add Ons
                        Tevatron
                          E17 resurvey (Check of as found by field crew) Pbar
                          Completed Topo @ 8Gev area next week (Conduit installed) Schedule Deep rod installation. 
   Accelerator Update Archive More InformationFor Tevatron luminosity charts and the current status of Fermilab's accelerators and detectors (live!), please go to Fermilab Now.
 Comments and SuggestionsWhat do you think about the Accelerator Updates? Please send comments and suggestions to: accelupdates@fnal.gov.
 
 |