| 
 
Monday March 15The day shift began with the Tevatron (TeV) ten-day shutdown just beginning.  Linac and Booster remain interlocked for special testing.
 
A Linac expert turned off the H- Source at 8:15 AM.
 
The Antiproton Source (Pbar) recovered from the planned feeder 24 power outage at 8:28 AM.
 
A RF expert took down the Main Injector (MI) and TeV RF at 8:37 AM.
 
At 9:15 AM, FESS technicians began cleaning the TeV pond strainers.
 
At 3:45 PM, Operations received a fire alarm for the Preaccelerator.  Operators responded and met the Fire Department.  They saw smoke in the H- Source area, but no fire.  Two Linac experts investigated further and believed the smoke was from a slipping belt for a vacuum pump.
 
A power supply tech repaired the Meson Center power supply (MC1D) that knocked the MCenter experiment off over the weekend.  It was a blown LCW hose.  The power supply must dry out before conducting any operational tests.
 
At 5:32 PM, operators manually turned off the MI60 sector pond water pumps; remote control wasn't working.  Pond water was leaking around the strainers into the service building because two pumps were running at the same time.  Typically, only one pump runs at a time.  Operators called in an expert to help straighten out the problem.
 
Tuesday March 16The midnight shift began with the second day of shutdown.
 
Cryo system techs began work on the TeV sector D1 wet engine at 6:42 AM.
 
Operations made Linac ready for access at 8 AM.
 
Operators finished interlocking all the Pbar tunnels and transfer lines at 5:30 PM for safety system tests.
 
Operators finished interlocking all the TeV enclosures at 8:49 PM for safety system tests.
 
Wednesday March 17The midnight shift began with the third day of shutdown.
 
At 6:40 AM, cryo system techs reported beginning work on various wet engines around the TeV ring.
 
A Partial List of Work Completed or Started
 
Linac
 
Installed 20 MHz digitizers
Pulled loss monitor cables
Installed loss monitors
Replaced filament controller for KRF1
 
Controls
 
Want to restart the Java nodes today to install new code; it should take about 2.5 hours
Troubleshoot a power supply UPS problem in MI
 
Booster
 
Installed vacuum control racks
Replaced the Dog13 power supply
Worked on kickers 
Fixed a flow switch
 
Main Injector
 
Completed the quadrupole magnet roles in the P1 line
 
Recycler
 
Installed loss monitor
Completed cable pulls in 62
Completed the re-buss for the Lambertson 52 magnet
Think they have found alignment problems for e-cool
 
TeV
 
The cryo system at A4 should be warm later today
The P-150 moves were completed
Completed the magnet roll measurements at sectors E and 1/2 of B
Continue work on the truck/quadrupole resonant noise problem
 
Cryo
 
The A4 cryo system warm-up will finish later today
Reported that they will have completed 17 wet engine overhauls by the end of the shutdown
 
Instrumentation
 
They have fixed the TeV sector E1 flying wire work as well as the Pbar flying wire work
Working on the MI DC current monitor 
Working on the MI8 BPM phase match problem
 
Pbar
 
They have completed seven of their forty-one jobs
 
RF
 
Conducting TeV and MI maintenance
 
Accelerator Update Archive
 
More InformationFor Tevatron luminosity charts and the current status of Fermilab's
accelerators and detectors (live!), please go to Fermilab Now
 
Comments and SuggestionsWhat do you think about the Accelerator Updates? Please send comments and suggestions to: accelupdates@fnal.gov.
 |