Contractor Assurance System Description

1.0 Introduction

Fermi National Accelerator Laboratory (Fermilab) is managed and operated by Fermi Research Alliance (FRA), LLC, under Contract DE-AC02-07CH11359 (prime contract) with the U.S. Department of Energy’s (DOE’s) Office of Science (SC). The prime contract Clause H.13 -Contractor Assurance System requires FRA to develop a Contractor Assurance System (CAS) that is executed by the contractor’s Board of Directors . The Contractor Assurance System, at a minimum, shall include the following key attributes:

  1. A comprehensive description of the assurance system with processes, key activities, and accountabilities clearly defined.
  2. A method for verifying/ensuring effective assurance system processes. Third party audits, peer reviews, independent assessments, and external certification (such as VPP and ISO9001 or ISO 14001) may be used.
  3. Text Box
  4. Timely notification of the DOE-Fermi Site Office (FSO) Contracting Officer of significant assurance system changes prior to changes.
  5. Rigorous, risk-based, credible self-assessments, and feedback and improvement reviews to assess and improve Fermilab’s work process and to carry out independent risk and vulnerability studies.
  6. Independent verification and correction of negative performance/compliance trends before they become significant issues.
  7. Integration of assurance system with other management systems including Integrated safety Management (ISM) .
  8. Metrics and targets to assess performance, including benchmarking of key functional areas with other DOE contractors, industry and research institutions. Assure development of metrics and targets that result in efficient and cost effective performance.
  9. Continuous feedback and performance improvement.
  10. An implementation plan (if needed) that considers and mitigates risks.
  11. Timely and appropriate communication to the FSO Contracting Officer, including electronic access, of assurance related information.

1.1 Purpose

The purpose of this document is to describe how the FRA and Fermilab’s current and proposed management programs, processes, and procedures work in concert to form a comprehensive CAS that meets the requirements of the prime contract.

1.2 Scope

CAS applies to all work activities and to all personnel performing work at Fermilab including subcontractors and guests. The CAS process encompasses all aspects of the eleven cross-cutting management systems which are essential to mission success.