Authorization Interoperability Closre

Start: September 10, 2008
Finish: October 14, 2008
Report Date: September 11, 2008

Gantt Chart

WBS Name Work
     
1 Test XACML / SAML library with different infrastructures 3d
1.1 Add tests on the wire for Interoperability Profile, testing C/Java libs interoperability (include all use cases: pilot jobs, PEP capabilities, ...) 3d
2 Integrate XACML/SAML library with existing infrastructures (PRIMA, GUMS, gLExec, LCAS/LCMAPS, ...) 57d
2.1 Develop parser for attribute certificates (PIP) according to Interop. XACML profile 25d
2.1.1 Develop Java parser (Developed as VOMS-PIP Incubator project, Aug, 08) 24d
2.1.2 Extend to include Resource, Action, and Environment contexts (?) 1d
2.2 Produce beta release of key client/servers integrating XACML lib 18d
2.2.1 Develop PEP/PDP L&L plug-in in C 2d
2.2.2 Develop PEP for GT2 / PRIMA 3d
2.2.3 Develop PDP-GUMS XACML interface in Java 10d
2.2.4 Develop PEP Globus-WS in Java
2.2.5 Develop PEP/PDP for Storage 3d
2.2.5.1 PEP/PDP gPlazma 3d
2.3 Produce v1 release of all client/servers with XACML lib 14d
2.3.1 Release production GUMS 2d
2.3.2 Release production SCAS 2d
2.3.3 Release production gPlazma 7d
2.3.4 Release production GT2 / gLExec / Prima 2d
2.3.5 Release production GT4 GRAM-WS 1d
3 Test interoperability 19d
3.1 Test gPlazma vs. GUMS 3d
3.2 Test gPlazma vs. SCAS 3d
3.3 Test Prima vs. GUMS 4d
3.3.1 Test SCAS client vs. GUMS 2d
3.3.2 Test integrated GT2, gridftp, and gLExec vs. GUMS 2d
3.4 Test Prima vs. SCAS 3d
3.4.1 Test SCAS client vs. SCAS 1d
3.4.2 Test integrated GT2, gridftp, and gLExec vs. SCAS 2d
3.5 Test GT4 Client GRAM-WS vs. GUMS 3d
3.6 Test GT4 Client GRAM-WS vs. SCAS 3d
4 Packaging , deployment, and user documentation 25d
4.1 GUMS 5d
4.2 GT2 and gLExec 5d
4.3 gPlazma / dCache 5d
4.4 SCAS 5d
4.5 GT4 GRAM-WS / Gridftp 5d
5 Project closure activities 5d
Week 39, 2008 Week 40, 2008 Week 41, 2008 Week 42, 2008
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14
, ,
,
,
,
,
,
,

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Test XACML / SAML library with different infrastructures Sep 10 Sep 12 3d
1.1 Add tests on the wire for Interoperability Profile, testing C/Java libs interoperability (include all use cases: pilot jobs, PEP capabilities, ...) Sep 10 Sep 12 3d 0%
2 Integrate XACML/SAML library with existing infrastructures (PRIMA, GUMS, gLExec, LCAS/LCMAPS, ...) Sep 10 Sep 25 57d
2.1 Develop parser for attribute certificates (PIP) according to Interop. XACML profile Sep 10 Sep 22 25d
2.1.1 Develop Java parser (Developed as VOMS-PIP Incubator project, Aug, 08) Sep 10 Sep 19 24d 0%
2.1.2 Extend to include Resource, Action, and Environment contexts (?) Sep 22 Sep 22 1d 0%
2.2 Produce beta release of key client/servers integrating XACML lib Sep 10 Sep 23 18d
2.2.1 Develop PEP/PDP L&L plug-in in C Sep 10 Sep 11 2d 0%
2.2.2 Develop PEP for GT2 / PRIMA Sep 10 Sep 11 3d 0%
2.2.3 Develop PDP-GUMS XACML interface in Java Sep 10 Sep 23 10d 0%
2.2.4 Develop PEP Globus-WS in Java Sep 23 Sep 23 100%
2.2.5 Develop PEP/PDP for Storage Sep 10 Sep 12 3d
2.2.5.1 PEP/PDP gPlazma Sep 10 Sep 12 3d 0%
2.3 Produce v1 release of all client/servers with XACML lib Sep 11 Sep 25 14d
2.3.1 Release production GUMS Sep 24 Sep 25 2d 0%
2.3.2 Release production SCAS Sep 12 Sep 15 2d 0%
2.3.3 Release production gPlazma Sep 15 Sep 23 7d 0%
2.3.4 Release production GT2 / gLExec / Prima Sep 11 Sep 15 2d 0%
2.3.5 Release production GT4 GRAM-WS Sep 23 Sep 23 1d 0%
3 Test interoperability Sep 16 Sep 30 19d
3.1 Test gPlazma vs. GUMS Sep 26 Sep 29 3d 0%
3.2 Test gPlazma vs. SCAS Sep 24 Sep 25 3d 0%
3.3 Test Prima vs. GUMS Sep 26 Sep 30 4d
3.3.1 Test SCAS client vs. GUMS Sep 26 Sep 26 2d 0%
3.3.2 Test integrated GT2, gridftp, and gLExec vs. GUMS Sep 29 Sep 30 2d 0%
3.4 Test Prima vs. SCAS Sep 16 Sep 17 3d
3.4.1 Test SCAS client vs. SCAS Sep 16 Sep 16 1d 100%
3.4.2 Test integrated GT2, gridftp, and gLExec vs. SCAS Sep 16 Sep 17 2d 0%
3.5 Test GT4 Client GRAM-WS vs. GUMS Sep 26 Sep 30 3d 0%
3.6 Test GT4 Client GRAM-WS vs. SCAS Sep 24 Sep 26 3d 0%
4 Packaging , deployment, and user documentation Sep 29 Oct 7 25d
4.1 GUMS Oct 1 Oct 7 5d 0%
4.2 GT2 and gLExec Oct 1 Oct 7 5d 0%
4.3 gPlazma / dCache Sep 29 Oct 6 5d 0%
4.4 SCAS Sep 29 Oct 3 5d 0%
4.5 GT4 GRAM-WS / Gridftp Oct 1 Oct 7 5d 0%
5 Project closure activities Oct 8 Oct 14 5d 0%

Resources

Name Short name Type Group Email Cost
Andrea Work 0
Gabriele Work 0
Igor Work 0
Jay Work 0
Oscar Work 0
Rachana Work 0
Ted Work 0