Charge for Director’s Preliminary Review
of the
NOvA Project
July 18-20, 2005
Will cover the Technical / Cost / Schedule / Management
aspects of the “project” to the extent plausible or sensible. It is recognized that this review is being
conducted at a very early stage of the NOvA project, thus it is a “preliminary”
review and material presented may not (will likely not) be developed to the
level of sophistication or detail of a more mature project.
Technical
- Are
the physics requirements stated? The
physics justification has been reviewed and Stage 1 approval was
recommended by the Fermilab Physics Advisory Committee (PAC).
- Have
these physics requirements been translated into technical performance
requirements / specifications?
- Can
the design be built? Does the
design meet the meet the technical specifications? Is it a reasonable design?
Cost
- Has a
Work Breakdown Structure (WBS) been developed or other listing of cost
elements been prepared?
- Do the
cost estimates for each WBS (or cost) element have a sound basis and are
they reasonable?
Schedule
- Is
there a schedule for the project?
- If, so
are the activity durations reasonable for the assumed resources?
- Has
the schedule been “resource loaded?”
Management
- Is
there an appropriate management organizational structure in place or
proposed to accomplish the design and construction?
- Have
responsibilities been assigned or have they been proposed?
- Are
there adequate staffing resources available or planned for this effort?
- Is
there a funding plan available or proposed to meet the resource
requirements to realize the detector?
The Director’s Review Committee is asked to present
findings, comments, and recommendations in a closeout session with the NOvA
Collaboration and Fermilab Management at the end of the review and in a written
report soon thereafter.